CAISO node intelligence

TESLA

ALAMEDA (CA) · PGAE · node key TESLA · CAISO run date 2026-10-12

Seven questions a developer, lender or counsel asks before filing here. Every figure is a CAISO row; Not public marks what the public files cannot answer and where to get it. Definitions: methodology.

Can you get in?

Official Cluster 16 POI statement: CONDITIONAL — Conceptual layout modification enables new 230 kV terminals [2026-01-15]
Not public: per-constraint transmission headroom at this POI — CAISO's cluster study reports (RIMS login).
Not on this site yet: the zonal transmission-capability table CAISO publishes for cluster scoring — public; the join is planned.

Who is ahead of you?

2,280 MW (n=8)
queued ahead of a new request (legacy + C15)
1,280 MW (n=5)
with an executed interconnection agreement · public report; C15 has no IA yet
436 MW (n=2)
operating at this node
1,000 MW
Cluster 15 requests seeking full capacity
Already operating within 5 km (EIA-860): 4 plants; 408 MW nameplate; 400 MW / 1,800 MWh storage; oldest unit 2018; 82 MW proposed. Technology: Batteries 400; Solar Photovoltaic 5; Other Natural Gas 3. Operators: Costco Wholesale; Kola Energy Storage, LLC; Powerflex; Prologis Logistics Services Incorporated. Owners: ESCA-PLD-TRACY4, LLC; Prologis, L.P.. Joined by distance to this node's mapped position, not by point of interconnection: a plant on a long gen-tie lands on the nearest substation. Corporate names from a federal filing.
Not public: who the interconnection customers are (the queue) — CAISO's public files carry project names only; the projects table below is the full public record. EIA-860 names the owners of what already operates nearby, not of what is queued.

Do projects leave after seeing the costs?

1,971 MW (n=10)
received Phase II / Facilities Study results here · any sheet, public report
255 MW (n=3)
of that, withdrew with results in hand
0.13 (n=10)
Phase II attrition (MW share)
Not public: the network upgrade cost allocated to a project here — Phase I / Phase II study reports, served through RIMS. Ask the incumbent developer or request the report; nothing public reconstructs it.

Will you be deliverable?

150 MW (n=1)
2025 TPD requested at this node
150 MW
allocated
0 MW
refused at 0 % — contracted / shortlisted (groups A+B)
0 MW
refused at 0 % — no PPA (group D)
2 / 0
2024 cycle: projects given full / partial capacity

A 0 % in group D is the expected result for an uncontracted project; a 0 % in group A or B is a contracted project that did not get deliverability. Rows are joined through all three sheets, so a request whose project has since withdrawn still appears. CAISO states no reason.

Will the power be worth anything here?

Outside Greater Bay Area local area boundary — Tesla is out of the Greater Bay Area and out of the Stockton (Tesla-Bellota) sub-area: a bulk station outside every local area named in the report Final 2027 LCT Report [2026-04-29]
Not on this site yet: day-ahead price history at this POI — CAISO OASIS publishes it; it is shown only for a pricing node confirmed by hand in data/poi_pnodes.csv, and this one is not confirmed yet.

Will the land pass intake?

Intake scoring under the 2023 IPE rewards site control, permitting progress and system need before study begins. Parcel, zoning, Williamson Act and CEC exclusion screens run for Kings and Kern counties (caiso-siting parcels, layers screen); results are in outputs/parcels_*.md for the nodes they were run on and are not yet rendered per node here.

Not public: landowner willingness and option terms — county assessor parcels give ownership class, not intent; owner names are withheld on purpose.

How long, and who gave up?

2,000 MW (n=5)
withdrawn since 2022 (both reports)
2,000 MW
of that, storage
0.77 (n=15)
storage churn · withdrawn storage ÷ queued + operating storage
0.33 (n=8)
Cluster 15 survival · active ÷ (active + withdrawn)
3,635 MW (n=12)
all-time withdrawn since 2006 · mostly wind/solar-era; colour, not signal
2026-06-01 to 2031-10-21
current on-line dates of active projects

Cluster-level time-to-withdrawal curves are on the Survival page; they compare process regimes, not only nodes.

Projects at this node (22)

Both reports. cod = current on-line date (public report) or proposed on-line date (Cluster 15). ia_status exists only in the public report. Cluster 15 deliverability is requested, not allocated.

project_namequeue_positionsheet_statusclusternet_mwstorage_mwdeliverabilityia_statuscodwithdrawn_date
ALTA CASA STORAGE1922ACTIVEC14500500FULL CAPACITYEXECUTED2031-10-21
Dove Cove2286ACTIVEC15500500FULL CAPACITY (REQ)2031-03-14
POTENTIA-VIRIDI1702ACTIVEC13400400FULL CAPACITYEXECUTED2028-05-11
ESPRESSO1912ACTIVEC14300300FULL CAPACITYEXECUTED2031-08-18
Galadriel2297ACTIVEC15300300FULL CAPACITY (REQ)2031-03-31
Emerita Energy Storage2221ACTIVEC15200200FULL CAPACITY (REQ)2028-03-01
MULQUEENEY RANCH WIND 21459ACTIVEC11600FULL CAPACITYEXECUTED2026-06-01
MULQUEENEY RANCH WIND1277ACTIVEC09200FULL CAPACITYEXECUTED2026-12-31
KOLA1275COMPLETEDC09400400FULL CAPACITYEXECUTED
GOLDEN HILLS 2 WIND709COMPLETEDC04360FULL CAPACITYEXECUTED
CPV CALIFORNIA VIII236WITHDRAWNSERIAL LGIP63002011-06-012008-11-26
Blue Oak Storage 22369WITHDRAWNC15600600FULL CAPACITY (REQ)2031-12-312025-12-03
Tea Leaf Energy Storage2285WITHDRAWNC15400400FULL CAPACITY (REQ)2030-06-012026-06-22
PATTERSON PASS GT PROJECT418WITHDRAWNSERIAL LGIP40002012-11-012008-11-25
POTENTIA-VIRIDI 22284WITHDRAWNC15400400FULL CAPACITY (REQ)2028-12-152025-05-20
WARDENCLYFFE1366WITHDRAWNC10300300FULL CAPACITY2022-12-312018-04-20
Ace2276WITHDRAWNC15300300FULL CAPACITY (REQ)2030-06-012025-12-02
Flamingo2287WITHDRAWNC15300300FULL CAPACITY (REQ)2030-06-012025-12-02
EAST-BAY-WIND1354WITHDRAWNC101500ENERGY ONLYIN PROGRESS2023-02-142021-05-20
RIPON GENERATION37WITHDRAWNAMEND 39750EXECUTED2011-12-31
BAY SUNSHINE HYBRID SOLAR1563WITHDRAWNC125050FULL CAPACITY2022-11-302019-07-09
COLINAS DE ORO1011WITHDRAWNC073030FULL CAPACITYEXECUTED2021-03-012021-01-11

TPD allocation requests at this node (3)

CAISO Transmission Plan Deliverability allocation results, joined on queue position through all three sheets of the public report (a request whose project has since withdrawn still appears). 2024 rows carry no MW. Groups: A = executed power purchase agreement requiring FCDS, or an LSE serving its own load; B = shortlisted for, or actively negotiating, a power purchase agreement; C = already in commercial operation for the capacity seeking TP deliverability; D = no PPA; electing the Section 8.9.2.3 (financial-security) path.

tpd_yearqueue_idproject_nameallocation_groupmw_requestedallocation_pctmw_allocatedstatus
20251912ESPRESSOD150100%150FCDSA
20241922ALTA CASA STORAGEB100%FCDSA
20241912ESPRESSOD100%FCDSA

WDAT requests at this substation (2)

WDAT = distribution-level queue at the same substation, PG&E file today; not CAISO deliverability. WDAT requests connect below CAISO's transmission grid; they carry no CAISO deliverability unless separately studied.

queue_positionstatus_rawprocessgen_typenet_mwrequest_receivedcurrent_codia_statusft_over_cap
3508-RDActiveFast TrackSolar PV22023-06-05Executed
1574-WDWithdrawnIndependent StudySolar PV202017-08-18Withdrawn

Geocode provenance

geo_method
exact
geo_score
1.00
osm_name
Tesla Substation
lat, lon
37.71205, -121.56474

All metrics

metricvaluedefinition
legacy_active_mw1,280active MW in the public report (C14 and earlier)
c15_active_mw1,000active MW in the Cluster 15 report
operating_mw436completed MW in the public report
pipeline_storage_mw2,200storage MW inside legacy_active_mw + c15_active_mw
operating_storage_mw400storage MW inside operating_mw (completed, public report)
wd_recent_mw2,000withdrawn in the last 5 years (both reports)
wd_recent_storage_mw2,000storage MW of those rows — each project's storage components capped at its net-to-grid figure; a handful of filings report net-to-grid as 0 and keep the component MW, so this can exceed the row above at 3 nodes.
wd_post_phase2_mw255withdrew AFTER Phase II / Facilities Study results (public report only)
p2_reached_mw1,971MW of projects that received Phase II / Facilities Study results here (public report, any sheet)
p2_withdrawn_mw255of those, MW that then withdrew (== wd_post_phase2_mw)
p2_attrition0.13p2_withdrawn_mw / p2_reached_mw — share of studied MW that left with results in hand
committed_mw1,280ACTIVE MW holding an executed interconnection agreement (public report)
churn_n15projects behind storage_churn (withdrawn recent + queued + operating)
c15_n8projects behind c15_survival
p2_n10projects behind p2_attrition
eia_plants4operable EIA-860 plants within 5 km of the node's mapped position (positioned nodes only)
eia_nameplate_mw408their nameplate MW, all technologies (EIA-860 Generator file, Operable sheet)
eia_storage_mwh1,800battery energy capacity among them (EIA-860 Energy Storage file), as reported
eia_storage_1h_mw0storage MW at units whose reported MWh is no more than their MW (one hour or less); shown with 'duration not established' because the value may reflect how the form was filled
eia_proposed_mw82nameplate MW in EIA-860's Proposed sheet within the same radius (planned / under construction)
wd_alltime_mw3,635every withdrawn MW since 2006 (includes dead wind/solar-era projects)
storage_churn0.77wd_recent_storage_mw / (active + operating storage MW) — the one to quote
churn_alltime1.34wd_alltime_mw / (pipeline + operating MW) — historical color only
c15_survival0.33c15_active / (c15_active + c15_withdrawn)
c15_fcds_req_mw1,000C15 active MW that requested Full Capacity Deliverability Status (requested, not allocated)
tpd25_projects1projects at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_req_mw150MW at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_alloc_mw150MW allocated in that cycle (requested × allocation %)
tpd25_denied_mw0MW requested by rows that received 0 %
tpd25_unalloc_mw0requested minus allocated: MW refused outright PLUS the remainder left by partial allocations — quote this for 'what the developer did not get'
tpd25_unknown_mw0MW requested by rows with no allocation percentage in the file; 0 today
tpd25_req_A_mw0of tpd25_req_mw, requested in allocation group A: executed PPA (or LSE own load)
tpd25_req_B_mw0of tpd25_req_mw, requested in allocation group B: shortlisted / negotiating a PPA
tpd25_req_C_mw0of tpd25_req_mw, requested in allocation group C: already in commercial operation
tpd25_req_D_mw150of tpd25_req_mw, requested in allocation group D: no PPA, Section 8.9.2.3 path
tpd25_denied_A_mw0of tpd25_denied_mw, refused at 0 % in group A
tpd25_denied_B_mw0of tpd25_denied_mw, refused at 0 % in group B
tpd25_denied_C_mw0of tpd25_denied_mw, refused at 0 % in group C
tpd25_denied_D_mw0of tpd25_denied_mw, refused at 0 % in group D
tpd25_denied_ppa_mw0refused MW in groups A + B: contracted or shortlisted projects that did not get deliverability; the refusal that matters
tpd24_fcdsa_projects2projects at the node allocated Full Capacity in the 2024 cycle
lcr_statusoutside Greater Bay AreaCAISO Local Capacity Area (Resource Adequacy geography): 'in <area>' or 'outside <area>' as the LCT report's boundary lists state it; blank = not encoded, never 'outside every area'
lcr_sub_areasub-area / load pocket within that area, when the LCT report delineates it
wdat_active_projects1active WDAT requests at the same substation (WDAT = distribution-level queue at the same substation, PG&E file today; not CAISO deliverability)
wdat_active_mw2MW of active WDAT (distribution-level) requests at the same substation (PG&E file today)
wdat_active_storage_mw0storage MW attributed from wdat_active_mw — an assumption: the PG&E file publishes one MW figure per request, so storage-only requests count in full and solar+storage requests count at half (160 of 1,011 active requests carry storage; 362 of their 479 MW is attributed as storage).
wdat_inservice_mw0WDAT MW already in service at that substation
wdat_withdrawn_mw20WDAT MW withdrawn at that substation (all-time in the file)
wdat_ft_over_cap_n0active Fast Track requests above the 5 MW Fast Track ceiling — held out of wdat_active_*
wdat_ft_over_cap_mw0MW of those held-out rows, as posted; cause not established

No figure on this site states a cause. CAISO files carry no withdrawal reason beyond "IC Request".

Screening tool, not engineering advice. Built from public filings by an engineer who is not a licensed PE. Verify every figure against the source filing named in its row before you rely on it for any decision. No warranty of any kind. Not affiliated with CAISO, EIA, or any utility. No engineering services are offered.