CAISO node intelligence

KRAMER SUBSTATION

SAN BERNARDINO (CA) · SCE · node key KRAMER · CAISO run date 2026-10-12

Seven questions a developer, lender or counsel asks before filing here. Every figure is a CAISO row; Not public marks what the public files cannot answer and where to get it. Definitions: methodology.

Can you get in?

No official Cluster 16 availability statement names this POI. Absence of a statement is not availability.

Not public: per-constraint transmission headroom at this POI — CAISO's cluster study reports (RIMS login).
Not on this site yet: the zonal transmission-capability table CAISO publishes for cluster scoring — public; the join is planned.

Who is ahead of you?

1,050 MW (n=5)
queued ahead of a new request (legacy + C15)
850 MW (n=4)
with an executed interconnection agreement · public report; C15 has no IA yet
432 MW (n=3)
operating at this node
0 MW
Cluster 15 requests seeking full capacity
Already operating within 5 km (EIA-860): 2 plants; 253 MW nameplate; 115 MW / 600 MWh storage; oldest unit 2023; 325 MW proposed. Technology: Solar Photovoltaic 138; Batteries 115. Operators: Resurgence Solar; Resurgence Solar II. Joined by distance to this node's mapped position, not by point of interconnection: a plant on a long gen-tie lands on the nearest substation. Corporate names from a federal filing.
Not public: who the interconnection customers are (the queue) — CAISO's public files carry project names only; the projects table below is the full public record. EIA-860 names the owners of what already operates nearby, not of what is queued.

Do projects leave after seeing the costs?

1,877 MW (n=11)
received Phase II / Facilities Study results here · any sheet, public report
395 MW (n=3)
of that, withdrew with results in hand
0.21 (n=11)
Phase II attrition (MW share)
Not public: the network upgrade cost allocated to a project here — Phase I / Phase II study reports, served through RIMS. Ask the incumbent developer or request the report; nothing public reconstructs it.

Will you be deliverable?

200 MW (n=1)
2025 TPD requested at this node
0 MW
allocated
0 MW
refused at 0 % — contracted / shortlisted (groups A+B)
200 MW
refused at 0 % — no PPA (group D)
1 / 0
2024 cycle: projects given full / partial capacity

A 0 % in group D is the expected result for an uncontracted project; a 0 % in group A or B is a contracted project that did not get deliverability. Rows are joined through all three sheets, so a request whose project has since withdrawn still appears. CAISO states no reason.

Will the power be worth anything here?

The Local Capacity Technical Report does not name this substation on any area boundary: not encoded, which is not the same as outside every area.

Not on this site yet: day-ahead price history at this POI — CAISO OASIS publishes it; it is shown only for a pricing node confirmed by hand in data/poi_pnodes.csv, and this one is not confirmed yet.

Will the land pass intake?

Intake scoring under the 2023 IPE rewards site control, permitting progress and system need before study begins. Parcel, zoning, Williamson Act and CEC exclusion screens run for Kings and Kern counties (caiso-siting parcels, layers screen); results are in outputs/parcels_*.md for the nodes they were run on and are not yet rendered per node here.

Not public: landowner willingness and option terms — county assessor parcels give ownership class, not intent; owner names are withheld on purpose.

How long, and who gave up?

150 MW (n=1)
withdrawn since 2022 (both reports)
0 MW
of that, storage
0.00 (n=9)
storage churn · withdrawn storage ÷ queued + operating storage
n/a (n=0)
Cluster 15 survival · active ÷ (active + withdrawn)
3,565 MW (n=19)
all-time withdrawn since 2006 · mostly wind/solar-era; colour, not signal
2023-08-06 to 2031-03-26
current on-line dates of active projects

Cluster-level time-to-withdrawal curves are on the Survival page; they compare process regimes, not only nodes.

Projects at this node (27)

Both reports. cod = current on-line date (public report) or proposed on-line date (Cluster 15). ia_status exists only in the public report. Cluster 15 deliverability is requested, not allocated.

project_namequeue_positionsheet_statusclusternet_mwstorage_mwdeliverabilityia_statuscodwithdrawn_date
DAGGETT SOLAR 31314ACTIVEC09300208FULL CAPACITYEXECUTED2023-08-06
ARATINA SOLAR CENTER 11204ACTIVEC08200125PARTIAL CAPACITYEXECUTED2026-06-01
ARATINA SOLAR CENTER 21604ACTIVEC12200113PARTIAL CAPACITYEXECUTED2026-12-31
WESTON STORAGE2101ACTIVEC14200200ENERGY ONLY2031-03-26
OVERNIGHT SOLAR1774ACTIVEC13150150FULL CAPACITYEXECUTED2026-11-13
DAGGETT SOLAR 21313COMPLETEDC09182131FULL CAPACITYEXECUTED
LOCKHART SOLAR 21617COMPLETEDC1215060FULL CAPACITYEXECUTED
SEGS EXPANSION 2 HYBRID1775COMPLETEDC1310045ENERGY ONLYEXECUTED
LEO WOLF ENERGY CENTER1771WITHDRAWNC13500500FULL CAPACITY2024-11-302020-09-08
LUZ SOLAR PARTNERS144WITHDRAWNSERIAL LGIP32002009-12-312009-12-07
SAND SOLAR1307WITHDRAWNC093000FULL CAPACITY2021-12-312018-05-15
RANDSBURG SOLAR ENERGY430WITHDRAWNSERIAL LGIP25002014-07-012011-03-22
MIRAGE SOLAR942WITHDRAWNC052500FULL CAPACITY2016-04-302013-03-18
FREMONT VALLEY PRESERVATION986WITHDRAWNC062450FULL CAPACITY2016-11-012014-04-17
CALIFORNIA SOLAR ONE160WITHDRAWNSERIAL LGIP22002009-01-012007-09-17
COSO SOLAR 21310WITHDRAWNC092060FULL CAPACITY2019-12-312017-02-14
GHOST TOWN SOLAR1306WITHDRAWNC092040FULL CAPACITY2020-12-312017-03-09
KRAMER SOLAR950WITHDRAWNC062000FULL CAPACITY2016-10-012014-03-06
LUZEN SOLAR ENERGY CENTER1772WITHDRAWNC13150150FULL CAPACITY2022-11-302020-06-30
GRAVEL HILLS WIND & SOLAR2099WITHDRAWNC141500FULL CAPACITY2025-10-012022-11-10
HARPER LAKE ENERGY STORAGE1202WITHDRAWNC08140140FULL CAPACITY2021-09-012016-03-10
COSO 2 SWAP (COSO FINANCE PARTNERS)643ADWITHDRAWNC03950FULL CAPACITY2012-07-012011-06-27
SEGS10 SOLAR1309WITHDRAWNC09810FULL CAPACITY2019-12-312017-02-14
KM ACQUISITIONS142WITHDRAWNSERIAL LGIP800EXECUTED2016-12-012017-01-09
HDLA SOLAR143WITHDRAWNSERIAL LGIP8002009-12-312008-11-26
COSO SOLAR 11311WITHDRAWNC09780FULL CAPACITY2018-12-312017-02-14
COSO #1391WITHDRAWNTC150FULL CAPACITY2010-01-112011-02-07

TPD allocation requests at this node (2)

CAISO Transmission Plan Deliverability allocation results, joined on queue position through all three sheets of the public report (a request whose project has since withdrawn still appears). 2024 rows carry no MW. Groups: A = executed power purchase agreement requiring FCDS, or an LSE serving its own load; B = shortlisted for, or actively negotiating, a power purchase agreement; C = already in commercial operation for the capacity seeking TP deliverability; D = no PPA; electing the Section 8.9.2.3 (financial-security) path.

tpd_yearqueue_idproject_nameallocation_groupmw_requestedallocation_pctmw_allocatedstatus
20252101WESTON STORAGED2000%0NONE
20241774OVERNIGHT SOLARA100%FCDSA

Geocode provenance

geo_method
exact
geo_score
1.00
osm_name
Kramer Substation
lat, lon
34.98970, -117.54220

All metrics

metricvaluedefinition
legacy_active_mw1,050active MW in the public report (C14 and earlier)
c15_active_mw0active MW in the Cluster 15 report
operating_mw432completed MW in the public report
pipeline_storage_mw796storage MW inside legacy_active_mw + c15_active_mw
operating_storage_mw236storage MW inside operating_mw (completed, public report)
wd_recent_mw150withdrawn in the last 5 years (both reports)
wd_recent_storage_mw0storage MW of those rows — each project's storage components capped at its net-to-grid figure; a handful of filings report net-to-grid as 0 and keep the component MW, so this can exceed the row above at 3 nodes.
wd_post_phase2_mw395withdrew AFTER Phase II / Facilities Study results (public report only)
p2_reached_mw1,877MW of projects that received Phase II / Facilities Study results here (public report, any sheet)
p2_withdrawn_mw395of those, MW that then withdrew (== wd_post_phase2_mw)
p2_attrition0.21p2_withdrawn_mw / p2_reached_mw — share of studied MW that left with results in hand
committed_mw850ACTIVE MW holding an executed interconnection agreement (public report)
churn_n9projects behind storage_churn (withdrawn recent + queued + operating)
c15_n0projects behind c15_survival
p2_n11projects behind p2_attrition
eia_plants2operable EIA-860 plants within 5 km of the node's mapped position (positioned nodes only)
eia_nameplate_mw253their nameplate MW, all technologies (EIA-860 Generator file, Operable sheet)
eia_storage_mwh600battery energy capacity among them (EIA-860 Energy Storage file), as reported
eia_storage_1h_mw0storage MW at units whose reported MWh is no more than their MW (one hour or less); shown with 'duration not established' because the value may reflect how the form was filled
eia_proposed_mw325nameplate MW in EIA-860's Proposed sheet within the same radius (planned / under construction)
wd_alltime_mw3,565every withdrawn MW since 2006 (includes dead wind/solar-era projects)
storage_churn0.00wd_recent_storage_mw / (active + operating storage MW) — the one to quote
churn_alltime2.41wd_alltime_mw / (pipeline + operating MW) — historical color only
c15_survivaln/ac15_active / (c15_active + c15_withdrawn)
c15_fcds_req_mw0C15 active MW that requested Full Capacity Deliverability Status (requested, not allocated)
tpd25_projects1projects at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_req_mw200MW at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_alloc_mw0MW allocated in that cycle (requested × allocation %)
tpd25_denied_mw200MW requested by rows that received 0 %
tpd25_unalloc_mw200requested minus allocated: MW refused outright PLUS the remainder left by partial allocations — quote this for 'what the developer did not get'
tpd25_unknown_mw0MW requested by rows with no allocation percentage in the file; 0 today
tpd25_req_A_mw0of tpd25_req_mw, requested in allocation group A: executed PPA (or LSE own load)
tpd25_req_B_mw0of tpd25_req_mw, requested in allocation group B: shortlisted / negotiating a PPA
tpd25_req_C_mw0of tpd25_req_mw, requested in allocation group C: already in commercial operation
tpd25_req_D_mw200of tpd25_req_mw, requested in allocation group D: no PPA, Section 8.9.2.3 path
tpd25_denied_A_mw0of tpd25_denied_mw, refused at 0 % in group A
tpd25_denied_B_mw0of tpd25_denied_mw, refused at 0 % in group B
tpd25_denied_C_mw0of tpd25_denied_mw, refused at 0 % in group C
tpd25_denied_D_mw200of tpd25_denied_mw, refused at 0 % in group D
tpd25_denied_ppa_mw0refused MW in groups A + B: contracted or shortlisted projects that did not get deliverability; the refusal that matters
tpd24_fcdsa_projects1projects at the node allocated Full Capacity in the 2024 cycle
lcr_statusCAISO Local Capacity Area (Resource Adequacy geography): 'in <area>' or 'outside <area>' as the LCT report's boundary lists state it; blank = not encoded, never 'outside every area'
lcr_sub_areasub-area / load pocket within that area, when the LCT report delineates it
wdat_active_projects0active WDAT requests at the same substation (WDAT = distribution-level queue at the same substation, PG&E file today; not CAISO deliverability)
wdat_active_mw0MW of active WDAT (distribution-level) requests at the same substation (PG&E file today)
wdat_active_storage_mw0storage MW attributed from wdat_active_mw — an assumption: the PG&E file publishes one MW figure per request, so storage-only requests count in full and solar+storage requests count at half (160 of 1,011 active requests carry storage; 362 of their 479 MW is attributed as storage).
wdat_inservice_mw0WDAT MW already in service at that substation
wdat_withdrawn_mw0WDAT MW withdrawn at that substation (all-time in the file)
wdat_ft_over_cap_n0active Fast Track requests above the 5 MW Fast Track ceiling — held out of wdat_active_*
wdat_ft_over_cap_mw0MW of those held-out rows, as posted; cause not established

No figure on this site states a cause. CAISO files carry no withdrawal reason beyond "IC Request".

Screening tool, not engineering advice. Built from public filings by an engineer who is not a licensed PE. Verify every figure against the source filing named in its row before you rely on it for any decision. No warranty of any kind. Not affiliated with CAISO, EIA, or any utility. No engineering services are offered.