CAISO node intelligence

IMPERIAL VALLEY SUBSTATION

IMPERIAL (CA) · SDGE · node key IMPERIAL VALLEY · CAISO run date 2026-10-12

Seven questions a developer, lender or counsel asks before filing here. Every figure is a CAISO row; Not public marks what the public files cannot answer and where to get it. Definitions: methodology.

Can you get in?

No official Cluster 16 availability statement names this POI. Absence of a statement is not availability.

Not public: per-constraint transmission headroom at this POI — CAISO's cluster study reports (RIMS login).
Not on this site yet: the zonal transmission-capability table CAISO publishes for cluster scoring — public; the join is planned.

Who is ahead of you?

875 MW (n=3)
queued ahead of a new request (legacy + C15)
875 MW (n=3)
with an executed interconnection agreement · public report; C15 has no IA yet
1,347 MW (n=9)
operating at this node
0 MW
Cluster 15 requests seeking full capacity
Already operating within 5 km (EIA-860): 3 plants; 478 MW nameplate; 331 MW / 724 MWh storage (200 MW of it at units reporting one hour or less; duration not established for those); oldest unit 2013; 299 MW proposed. Technology: Batteries 331; Solar Photovoltaic 147. Operators: Big Rock ESS Assets, LLC; RWE Clean Energy; Southern Power Co. Owners: Campo Verde Solar, LLC. Joined by distance to this node's mapped position, not by point of interconnection: a plant on a long gen-tie lands on the nearest substation. Corporate names from a federal filing.
Not public: who the interconnection customers are (the queue) — CAISO's public files carry project names only; the projects table below is the full public record. EIA-860 names the owners of what already operates nearby, not of what is queued.

Do projects leave after seeing the costs?

5,453 MW (n=23)
received Phase II / Facilities Study results here · any sheet, public report
3,231 MW (n=11)
of that, withdrew with results in hand
0.59 (n=23)
Phase II attrition (MW share)
Not public: the network upgrade cost allocated to a project here — Phase I / Phase II study reports, served through RIMS. Ask the incumbent developer or request the report; nothing public reconstructs it.

Will you be deliverable?

777 MW (n=3)
2025 TPD requested at this node
0 MW
allocated
177 MW
refused at 0 % — contracted / shortlisted (groups A+B)
600 MW
refused at 0 % — no PPA (group D)
1 / 0
2024 cycle: projects given full / partial capacity

A 0 % in group D is the expected result for an uncontracted project; a 0 % in group A or B is a contracted project that did not get deliverability. Rows are joined through all three sheets, so a request whose project has since withdrawn still appears. CAISO states no reason.

Will the power be worth anything here?

Local Capacity Area: San Diego-Imperial Valley Final 2027 LCT Report [2026-04-29]
Not on this site yet: day-ahead price history at this POI — CAISO OASIS publishes it; it is shown only for a pricing node confirmed by hand in data/poi_pnodes.csv, and this one is not confirmed yet.

Will the land pass intake?

Intake scoring under the 2023 IPE rewards site control, permitting progress and system need before study begins. Parcel, zoning, Williamson Act and CEC exclusion screens run for Kings and Kern counties (caiso-siting parcels, layers screen); results are in outputs/parcels_*.md for the nodes they were run on and are not yet rendered per node here.

Not public: landowner willingness and option terms — county assessor parcels give ownership class, not intent; owner names are withheld on purpose.

How long, and who gave up?

2,435 MW (n=7)
withdrawn since 2022 (both reports)
2,385 MW
of that, storage
2.45 (n=19)
storage churn · withdrawn storage ÷ queued + operating storage
0.00 (n=1)
Cluster 15 survival · active ÷ (active + withdrawn)
12,100 MW (n=40)
all-time withdrawn since 2006 · mostly wind/solar-era; colour, not signal
2027-01-18 to 2032-06-01
current on-line dates of active projects

Cluster-level time-to-withdrawal curves are on the Survival page; they compare process regimes, not only nodes.

Projects at this node (52)

Both reports. cod = current on-line date (public report) or proposed on-line date (Cluster 15). ia_status exists only in the public report. Cluster 15 deliverability is requested, not allocated.

project_namequeue_positionsheet_statusclusternet_mwstorage_mwdeliverabilityia_statuscodwithdrawn_date
SILVER RIDGE MOUNT SIGNAL124ACTIVESERIAL LGIP600150PARTIAL CAPACITYEXECUTED2027-06-01
SUNRISE BUTTE1667ACTIVEC12150150PARTIAL CAPACITYEXECUTED2027-01-18
LECONTE ENERGY STORAGE1175ACTIVEC08125125PARTIAL CAPACITYEXECUTED2032-06-01
BATERIA DEL SUR1531COMPLETEDC11350350FULL CAPACITYEXECUTED
BIG ROCK SOLAR FARM1166COMPLETEDC08200200PARTIAL CAPACITYEXECUTED
IMPERIAL VALLEY WEST608COMPLETEDC021500FULL CAPACITYEXECUTED
CAMPO VERDE SOLAR (FKA USS WIXOM SOLAR 1)590COMPLETEDC021470FULL CAPACITYEXECUTED
IV SUBSTATION SOUTH510COMPLETEDC011300FULL CAPACITYEXECUTED
CENTINELA SOLAR ENERGY442COMPLETEDTC1250FULL CAPACITYEXECUTED
WISTARIA RANCH SOLAR ENERGY429COMPLETEDTC1000FULL CAPACITYEXECUTED
BLUE HORNET SOLAR838COMPLETEDC041000FULL CAPACITYEXECUTED
CENTINELA SOLAR ENERGY EXPANSION (45 MW) 643AMCOMPLETEDC03450FULL CAPACITYEXECUTED
BAJANORTE WIND FACILITY164WITHDRAWNSERIAL LGIP1,00002010-10-012008-11-19
VIENTO MEXICANA168WITHDRAWNSERIAL LGIP1,00002011-12-312011-03-31
IMPERIAL VALLEY GENERATION PROJECT604WITHDRAWNC026000FULL CAPACITY2014-04-012010-11-24
YUHA DESERT BATTERY STORAGE2176WITHDRAWNC14600600ENERGY ONLY2031-11-052026-05-28
SANTA CATARINA WIND764WITHDRAWNC045080FULL CAPACITY2014-12-312012-03-13
MEXICO WIND178BWITHDRAWNSERIAL LGIP50002010-06-152011-03-31
RE AUSTIN643UWITHDRAWNC035000FULL CAPACITY2014-01-302011-09-09
VOLTA DE MEXICALI1664WITHDRAWNC12500500ENERGY ONLY2035-03-102025-09-06
BLACK ROCK 1,2,3,4, & 5,6677WITHDRAWNC044700FULL CAPACITY2015-06-162012-03-20
YUHA BASIN HYBRID SOLAR ENERGY PROJECT405WITHDRAWNSERIAL LGIP45002012-12-312008-11-26
WESTSIDE CANAL ENERGY CENTER1437WITHDRAWNC10425400ENERGY ONLY2021-12-312020-06-10
HICKORY SOLAR FARM713WITHDRAWNC044000FULL CAPACITY2014-07-012011-06-16
SALTON SOLAR1666WITHDRAWNC12400211FULL CAPACITY2023-12-012020-03-04
BIG HORN ENERGY STORAGE1827WITHDRAWNC13400400FULL CAPACITY2024-07-012024-02-21
KINGSLEY SOLAR FARM1665WITHDRAWNC12360360ENERGY ONLYEXECUTED2030-01-312026-08-25
DREW ROAD GENERATION984WITHDRAWNC063440FULL CAPACITY2018-01-012013-07-15
SES SOLAR TWO)78WITHDRAWNSERIAL LGIP30002012-05-312012-03-02
AUBANEL I WIND PROJECT643BWITHDRAWNC033000ENERGY ONLY2012-06-302010-11-26
IMPERIAL SOLAR 1414WITHDRAWNSERIAL LGIP28002012-07-012008-11-21
SOLAR DE MEXICALI2162WITHDRAWNC14275275FULL CAPACITY2030-03-162026-04-07
SILVER LEAF SOLAR643VWITHDRAWNC032500FULL CAPACITY2013-09-302011-09-09
IMPERIAL SOLEIL169WITHDRAWNSERIAL LGIP21202011-12-312008-11-26
LAGUNA SALADA PV POWER PLANT961WITHDRAWNC062010FULL CAPACITYEXECUTED2020-04-032019-08-01
MOUNT SIGNAL SOLAR FARM561WITHDRAWNC022000FULL CAPACITY2014-12-012013-07-11
MOUNT SIGNAL SOLAR FARM II643AOWITHDRAWNC032000FULL CAPACITY2014-06-012011-08-11
MOUNT SIGNAL SOLAR FARM III735WITHDRAWNC042000FULL CAPACITY2014-06-012011-12-21
CARDINAL STORAGE1658WITHDRAWNC12200200ENERGY ONLY2028-10-122022-04-18
ACORN GREENWORKS667WITHDRAWNC041500FULL CAPACITYEXECUTED2021-12-312018-06-19
SILVERTREE GREENWORKS766WITHDRAWNC041500FULL CAPACITY2014-12-312012-03-30
RANCHO WISTARIA SOLAR ENERGY CENTER985WITHDRAWNC061500FULL CAPACITY2016-12-312014-03-19
WISTARIA SOLAR 21436WITHDRAWNC101500FULL CAPACITY2019-12-312017-06-05
Amberjill Energy2213WITHDRAWNC1510050ENERGY ONLY (REQ)2029-07-312025-12-03
SONORA SOLAR GENERATING STATION454WITHDRAWNSERIAL LGIP8402011-02-012008-11-26
YUHA BASIN SOLAR919WITHDRAWNC05750FULL CAPACITY2015-01-012013-03-04
SILVERLEAF SOLAR II875WITHDRAWNC05600FULL CAPACITY2014-12-312012-08-02
CENTINELA SOLAR ENERGY EXPANSION II - 45 MW EXPANSION685WITHDRAWNC04450ENERGY ONLY2014-09-012012-04-10
OCOTILLO SOL PROJECT621WITHDRAWNSGIP-TC200ENERGY ONLY2017-03-032016-02-16
VALLE DEL SOL848WITHDRAWNC04200FULL CAPACITY2013-12-012012-04-04
BCS ENERGY STORAGE1041WITHDRAWNC072020FULL CAPACITY2015-06-012015-01-22
CENTINELA SOLAR ENERGY FACILITY 2MWFT1090WITHDRAWNFT22ENERGY ONLY2015-01-152014-09-04

TPD allocation requests at this node (5)

CAISO Transmission Plan Deliverability allocation results, joined on queue position through all three sheets of the public report (a request whose project has since withdrawn still appears). 2024 rows carry no MW. Groups: A = executed power purchase agreement requiring FCDS, or an LSE serving its own load; B = shortlisted for, or actively negotiating, a power purchase agreement; C = already in commercial operation for the capacity seeking TP deliverability; D = no PPA; electing the Section 8.9.2.3 (financial-security) path.

tpd_yearqueue_idproject_nameallocation_groupmw_requestedallocation_pctmw_allocatedstatus
20251175LECONTE ENERGY STORAGEB850%0NONE
2025124SILVER RIDGE MOUNT SIGNALB920%0NONE
20252176YUHA DESERT BATTERY STORAGED6000%0NONE
20241531BATERIA DEL SURA100%FCDSA
20241531BATERIA DEL SURA100%FCDSA

Geocode provenance

geo_method
exact
geo_score
1.00
osm_name
Imperial Valley Substation
lat, lon
32.71791, -115.71556

All metrics

metricvaluedefinition
legacy_active_mw875active MW in the public report (C14 and earlier)
c15_active_mw0active MW in the Cluster 15 report
operating_mw1,347completed MW in the public report
pipeline_storage_mw425storage MW inside legacy_active_mw + c15_active_mw
operating_storage_mw550storage MW inside operating_mw (completed, public report)
wd_recent_mw2,435withdrawn in the last 5 years (both reports)
wd_recent_storage_mw2,385storage MW of those rows — each project's storage components capped at its net-to-grid figure; a handful of filings report net-to-grid as 0 and keep the component MW, so this can exceed the row above at 3 nodes.
wd_post_phase2_mw3,231withdrew AFTER Phase II / Facilities Study results (public report only)
p2_reached_mw5,453MW of projects that received Phase II / Facilities Study results here (public report, any sheet)
p2_withdrawn_mw3,231of those, MW that then withdrew (== wd_post_phase2_mw)
p2_attrition0.59p2_withdrawn_mw / p2_reached_mw — share of studied MW that left with results in hand
committed_mw875ACTIVE MW holding an executed interconnection agreement (public report)
churn_n19projects behind storage_churn (withdrawn recent + queued + operating)
c15_n1projects behind c15_survival
p2_n23projects behind p2_attrition
eia_plants3operable EIA-860 plants within 5 km of the node's mapped position (positioned nodes only)
eia_nameplate_mw478their nameplate MW, all technologies (EIA-860 Generator file, Operable sheet)
eia_storage_mwh724battery energy capacity among them (EIA-860 Energy Storage file), as reported
eia_storage_1h_mw200storage MW at units whose reported MWh is no more than their MW (one hour or less); shown with 'duration not established' because the value may reflect how the form was filled
eia_proposed_mw299nameplate MW in EIA-860's Proposed sheet within the same radius (planned / under construction)
wd_alltime_mw12,100every withdrawn MW since 2006 (includes dead wind/solar-era projects)
storage_churn2.45wd_recent_storage_mw / (active + operating storage MW) — the one to quote
churn_alltime5.45wd_alltime_mw / (pipeline + operating MW) — historical color only
c15_survival0.00c15_active / (c15_active + c15_withdrawn)
c15_fcds_req_mw0C15 active MW that requested Full Capacity Deliverability Status (requested, not allocated)
tpd25_projects3projects at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_req_mw777MW at the node that sought TPD in CAISO's 2025 allocation cycle
tpd25_alloc_mw0MW allocated in that cycle (requested × allocation %)
tpd25_denied_mw777MW requested by rows that received 0 %
tpd25_unalloc_mw777requested minus allocated: MW refused outright PLUS the remainder left by partial allocations — quote this for 'what the developer did not get'
tpd25_unknown_mw0MW requested by rows with no allocation percentage in the file; 0 today
tpd25_req_A_mw0of tpd25_req_mw, requested in allocation group A: executed PPA (or LSE own load)
tpd25_req_B_mw177of tpd25_req_mw, requested in allocation group B: shortlisted / negotiating a PPA
tpd25_req_C_mw0of tpd25_req_mw, requested in allocation group C: already in commercial operation
tpd25_req_D_mw600of tpd25_req_mw, requested in allocation group D: no PPA, Section 8.9.2.3 path
tpd25_denied_A_mw0of tpd25_denied_mw, refused at 0 % in group A
tpd25_denied_B_mw177of tpd25_denied_mw, refused at 0 % in group B
tpd25_denied_C_mw0of tpd25_denied_mw, refused at 0 % in group C
tpd25_denied_D_mw600of tpd25_denied_mw, refused at 0 % in group D
tpd25_denied_ppa_mw177refused MW in groups A + B: contracted or shortlisted projects that did not get deliverability; the refusal that matters
tpd24_fcdsa_projects1projects at the node allocated Full Capacity in the 2024 cycle
lcr_statusin San Diego-Imperial ValleyCAISO Local Capacity Area (Resource Adequacy geography): 'in <area>' or 'outside <area>' as the LCT report's boundary lists state it; blank = not encoded, never 'outside every area'
lcr_sub_areasub-area / load pocket within that area, when the LCT report delineates it
wdat_active_projects0active WDAT requests at the same substation (WDAT = distribution-level queue at the same substation, PG&E file today; not CAISO deliverability)
wdat_active_mw0MW of active WDAT (distribution-level) requests at the same substation (PG&E file today)
wdat_active_storage_mw0storage MW attributed from wdat_active_mw — an assumption: the PG&E file publishes one MW figure per request, so storage-only requests count in full and solar+storage requests count at half (160 of 1,011 active requests carry storage; 362 of their 479 MW is attributed as storage).
wdat_inservice_mw0WDAT MW already in service at that substation
wdat_withdrawn_mw0WDAT MW withdrawn at that substation (all-time in the file)
wdat_ft_over_cap_n0active Fast Track requests above the 5 MW Fast Track ceiling — held out of wdat_active_*
wdat_ft_over_cap_mw0MW of those held-out rows, as posted; cause not established

No figure on this site states a cause. CAISO files carry no withdrawal reason beyond "IC Request".

Screening tool, not engineering advice. Built from public filings by an engineer who is not a licensed PE. Verify every figure against the source filing named in its row before you rely on it for any decision. No warranty of any kind. Not affiliated with CAISO, EIA, or any utility. No engineering services are offered.